Mulund Goregaon Link Road is now on Fast Track

Mulund Goregaon Link Road is now on Fast Track
Originally Proposed in 1962 Development Plan
Now Design, Action Plan Finalised Process Started
Phase 1
1: Widening of approach road to Nahur RoB Railway Bridge Work order given, soil testing started
2 Widening of RoB Rail Over Bridge at Nahur designs given to Railways, sent to IIT for vetting. Railway has to execute
Phase 2:
Widening of A K Vaidya Marg and Pipeline Road: Tenders floated, due date 28th April
Phase 3:
Tunnel under SGNY Vihar Lake National Park : Geotech investigations complete, 4.7 km tunnel proposed of 3+3 lanes. Forest and Environmental Clearanace being prepared, tender documents being prepared.